The Port Authority of NY & NJ LaGuardia Airport Hangar #7 - 1st Floor Flushing, NY 11371 Tel. (718) 533-3539
|
Date Completed: |
11/09/2022 |
Final Value:
|
$4,335,150 |
|
|
- Reconstruction of the substructure pile supported runway extensions of Runway 13 and 22 at LaGuardia Airport
- All work to be completed during periods of low tide utilizing our company custom work barges
- Furnish and install new pile wraps: 76 EA
- Furnish and install new sacrificial anodes: 670 EA
- Pile Cap reconstruction: 13 EA
- Pile and precast pre-stressed girder spall repairs: 480 SF
- Crack Injection Repairs: 24 LF
- Pre-stressed Girder Type 2 Repair Steel Jackets: 4 EA
- Emergency Runway Expansion Joint Repairs & Replacement.
- Bulkhead Repairs at Outfall #4
- Runway Deck Repairs - 1,033 SF
|
|